[wp-hackers] 2.3 Dev Cycle

Geoffrey Sneddon foolistbar at googlemail.com
Thu May 17 12:13:55 GMT 2007


On 17 May 2007, at 01:47, Matt Mullenweg wrote:

> Geoffrey Sneddon wrote:
>> Can I just please say that we should (if we're on a 120 day  
>> release cycle) have every major code change within the first 40  
>> days? Then after 80 days enter a feature freeze? That thereby  
>> leaves another 40 days purely of QA, and would hopefully avoid any  
>> chaos like we had with tagging in 2.2.
>
> This is the official goal:
>
> http://comox.textdrive.com/pipermail/wp-hackers/2006-October/ 
> 008907.html

Then why did tagging go in so late into 2.2?

It shouldn't be a goal, rather as much a requirement.


- Geoffrey Sneddon